on september 25, cnooc limited announced that the bozhong 28-2 south oilfield second adjustment project has commenced production. the project is located in southern bohai sea, with an average water depth of around 21 meters. the main production facilities include 1 central platform and 1 water-injection subsea pipeline. 21 development wells are planned to be commissioned, including 13 production wells and 8 water-injection wells. it is expected to achieve a peak production of approximately 7,600 barrels of crude oil per day in 2024. cnooc limited holds 100% interest in the project and acts as the operator.
|